Michels Pipeline

Local Union

190

Job Notification Date

03/19/2019

Contractor

Michels Pipeline

Company

Northwestern Energy

state

Montana

Work

Install approx. 29,800 feet of 12.75 inch O.D. x 0.250 inch wall API 5L grade X-52 pipe coated with a nominal 14 mil thickness of fusion bonded epoxy via trenching, installation of approx. 9,850 feet of 12.75 in O.D. x 0.312 inch wall API 5L grade X-52 pipe coated with 14 mil thickness of fusion bonded epoxy, 30 mil thickness of abrasion resistant overlay via HDD.  Installation of approx. 760 feet of 8.625 inch O. D. x 0.322 inch wall API 5L Grade X-52 resistant overlay viz trenching in Billings, Yellowstone County, MT

Superintendent

Cory Vandervoorden

Start Date

03/18/2019